Sector Brief

Nuclear Fusion

Companies pursuing the holy grail of energy: harnessing the power of the stars through nuclear fusion for virtually limitless clean electricity.

State of the Industry

Updated 2026-09-03

06 Companies

Commonwealth Fusion Systems logo

Commonwealth Fusion Systems

Private

Commonwealth Fusion Systems is building commercial fusion systems around high-temperature superconducting magnet technology developed with MIT. SPARC, its fusion-energy demonstration tokamak under construction in Devens, Massachusetts, reached ~80% completion by the end of July 2026: the first of 18 toroidal-field magnets was installed in January and the second 48-ton vacuum-vessel half arrived in May, with all 18 magnets targeted by end of summer 2026 ahead of first plasma and a Q>1 net-energy attempt in 2027. ARC, CFS' first commercial plant - officially named the Fall Line Fusion Power Station and sited on 100 acres in Chesterfield County, Virginia - became in April 2026 the first fusion project to file for grid interconnection with PJM, and on June 4, 2026 CFS published a five-paper ARC Physics Basis in the Journal of Plasma Physics projecting ~1.1 GW of fusion power and ~400 MW of net electricity. CFS has also begun monetizing its HTS magnet platform, signing a potentially multi-billion-dollar long-term magnet supply deal with Realta Fusion and launching a SPARC digital twin program with Nvidia and Siemens, and in July 2026 became the first international partner in the UK Atomic Energy Authority's £220M LIBRTI tritium-breeding program to tackle fusion's fuel-supply challenge. On July 30, 2026 CFS closed $1B more from pension and sovereign-wealth funds (bringing total capital to $4B) and named former Moderna CFO Lorence Kim - who led that company's 2018 IPO - as its new chief financial officer, a hire widely read as early positioning for a future CFS public listing.

Founded 2018🇺🇸Devens, Massachusetts
Total Funding

~$4B

SPARC Target Performance

Q ~11 and ~140 MW fusion power

SPARC Build Progress

~80% complete (both vacuum vessel halves in Tokamak Hall; magnets installing)

SPARC TF Magnets Installed

Installation under way; all 18 targeted by end of summer 2026

ARC Target Output

~400 MW (Fall Line Fusion Power Station, Chesterfield County, VA)

Commercial Offtake Secured

Google 200 MW PPA + Eni $1B+ offtake from first ARC plant

Helion Energy logo

Helion Energy

Private

Helion Energy is building fusion generators aimed at producing commercial electricity from fusion. Its Polaris prototype began operating in late 2024 and in February 2026 became the first privately developed fusion machine to demonstrate measurable deuterium-tritium fusion at 150 million degrees Celsius, a temperature record that still stood as of August 2026. Helion is now advancing Orion in Malaga, Washington, where site work began in 2025 for the company's first commercial machine intended to deliver electricity from fusion to Microsoft; in June 2026 Washington State made Helion the first company in the world to secure the regulatory licenses needed to build and operate a fusion power plant, and construction has since moved to the fusion generator building. A smaller new 'Tiny Merge' testbed is being integrated at the Everett campus to iterate on plasma formation faster. On June 4, 2026 Helion closed a $465M Series G led by Thrive Capital at a $15.5B post-money valuation, lifting total funding to roughly $1.5B; OpenAI remains in unsigned, advanced talks to buy fusion power from Helion at gigawatt scale as of August 2026, a negotiation that prompted Sam Altman to step down as Helion board chair on March 23, 2026 to recuse himself, and that has since drawn Congressional inquiry and courtroom scrutiny over his personal stake in Helion.

Founded 2013🇺🇸Everett, Washington
Total Funding

~$1.5B invested (incl. June 2026 Series G)

Plasma Temperature

150 million °C (13 keV) - standing private-fusion record; ~200M °C targeted for a commercial plant

Commercial Commitments

50+ MWe for Microsoft; 500 MWe planned with Nucor; OpenAI 5 GW (2030) / 50 GW (2035) under negotiation, still unsigned as of August 2026

Valuation

$15.5B post-money (June 2026 Series G)

Pacific Fusion logo

Pacific Fusion

Private

Pacific Fusion is taking the inertial route to fusion rather than the magnetic one: instead of holding plasma in a magnetic bottle, it crushes a small capsule of deuterium-tritium fuel with an enormous, extremely fast electrical pulse. The company's distinguishing technology is the impedance-matched Marx generator, a pulser architecture that is simpler and cheaper than the systems used at national laboratories, and its plan is to gang 156 production-scale pulser modules into a Demonstration System designed to reach net facility gain - more fusion energy out than the total energy stored in the machine - by 2030. Founded in 2023 by Eric Lander, Keith LeChien, Will Regan, Carrie von Muench and Leland Ellison, it launched publicly in October 2024 with a roughly $900M Series A led by General Catalyst that is released in tranches against technical milestones; the round has since passed $1B as those milestones cleared. In June 2026 a scaled module prototype delivered more than 440 gigawatts at about 1.1 megavolts in an 80-nanosecond pulse, and in July 2026 the Sirius prototype at Lawrence Livermore National Laboratory passed 3,000 full-power shots at 95% energy efficiency. Pacific Fusion broke ground on its $1B research and manufacturing campus at Mesa del Sol in Albuquerque, New Mexico, on August 25, 2026 - the National Nuclear Security Administration signed a fusion-research MOU with the company the same day - and Nature reporters visiting the nearby Los Lunas build center that month found two of the more than 150 full-scale pulser modules the Demonstration System needs already completed. The machine is designed to produce more than 100 megajoules of fusion output per pulse, about 10 times NIF's record output.

Founded 2023🇺🇸Fremont, California
Total Funding

>$1B Series A (released in milestone-based tranches)

Scaled Prototype Output

440+ GW peak power, ~1.1 MV, 80 ns pulse (June 2026)

Sirius Shot Count

3,000 full-power shots at 95% energy efficiency

Demonstration System

156 pulser modules, net facility gain targeted by 2030; 2 full-scale modules completed as of August 2026

New Mexico Campus

$1B at Mesa del Sol, Albuquerque; ~200 permanent jobs; groundbreaking held August 25, 2026

Design Target vs NIF

100x higher facility gain at 10x lower cost

Users Program

EOI phase launched March 2026 (closed March 31); proposals call 2027; first external experiments 2029

Design Fusion Output Target

100+ MJ of fusion output per pulse from ~80 MJ of stored electrical energy, versus NIF's 3.15 MJ record output

Proxima Fusion logo

Proxima Fusion

Private

Proxima Fusion is Europe's best-funded fusion company and the first research spin-off from the Max Planck Institute for Plasma Physics, founded in Munich in 2023 to commercialize the stellarator - a twisted magnetic bottle that is harder to build than a tokamak but runs continuously without needing to drive a current through the plasma. Its quasi-isodynamic design, Stellaris, was published in February 2025 as the first peer-reviewed, fully integrated stellarator power plant concept. In February 2026 Proxima signed a memorandum of understanding with RWE, the Free State of Bavaria and the Max Planck IPP to build Alpha, a roughly €2B net-energy demonstrator at Garching near Munich targeted to begin operating in 2031, followed by a commercial Stellaris plant at the decommissioned Gundremmingen nuclear site later in the 2030s; an Alpha Alliance of more than 30 European industrial companies including Siemens Energy, Framatome, Air Liquide and Thales was announced the day before. On July 7, 2026 the company raised €411M ($468M) at a €2.4B ($2.7B) valuation, led by XTX Ventures and East X Ventures with RWE and Google as strategic investors, taking total funding past €650M and funding completion of its Stellarator Model Coil in 2027.

Founded 2023🇬🇪🇷🇲🇦🇳🇾Munich, Germany
Total Funding

>€650M (including €95M in public grants)

Valuation

€2.4B ($2.7B) post-money (July 2026)

Alpha Demonstrator

~€2B, Garching near Munich, operations targeted 2031

Industrial Partners

30+ companies in the Alpha Alliance

Sites

3 (Munich HQ; Paul Scherrer Institute, Switzerland; Culham, UK)

STRIDE National Fusion Hub

~€125M initial BMFTR funding across a phased Aug 2026-Dec 2029 program with 34 initial academic and industrial partners; coordinated with Gauss Fusion and Max Planck IPP

TAE Technologies logo

TAE Technologies

Private (proposed TMTG merger; targeted Q4 2026 close)

TAE Technologies is a private fusion company developing hydrogen-boron fusion with a beam-driven field-reversed-configuration architecture. Its 2025 'Norm' breakthrough reduced reactor complexity enough to skip the planned Copernicus step and move directly toward Da Vinci, its first prototype power plant. In 2026 TAE completed its multi-state site evaluation tour for the first 50 MWe plant (Alabama, Ohio, Texas), formally established the TAE Beam UK joint venture with UKAEA at Culham to commercialize neutral-beam accelerator technology, and is now targeting a Q4 2026 close of its $6B all-stock merger with Trump Media & Technology Group, which in June 2026 confirmed it will no longer spin off Truth Social and other media assets ahead of the deal. TAE Power Solutions and TAE Life Sciences commercialize adjacent power-delivery and oncology technologies derived from its fusion R&D.

Founded 1998🇺🇸Foothill Ranch, California
Total Funding

>$1.3B equity raised since inception (plus $200M TMTG cash at signing, additional $100M upon S-4 filing)

Proposed TMTG Merger Value

$6B+ all-stock; ~50/50 fully-diluted equity split; targeted to close by end of 2026 (reaffirmed in TMTG's Aug 10, 2026 8-K and again in TAE's Aug 5, 2026 Black Moon Energy release); Form S-4 still not filed as of late August 2026, though TMTG says it intends to file using its Q2 2026 financials

Granted Patents

>1,600

Norm Plasma Temperature

70+ million °C (steady-state FRC; upgrade to 100M °C underway)

Da Vinci Initial Output

~50 MWe (early 2030s); follow-on plants 350–500 MWe

TAE Beam UK Funding

£5.6M UKAEA equity + TAE nine-figure investment

Tokamak Energy logo

Tokamak Energy

Private

Tokamak Energy is a UK fusion company spun out of the UK Atomic Energy Authority in 2009 that pairs two bets: the spherical tokamak, a squashed-sphere reactor shape that holds plasma more efficiently than a conventional doughnut, and high-temperature superconducting (HTS) magnets built in-house. Its ST40 machine reached 100 million degrees Celsius in 2022 and closed out its 2025 campaign with three records - 1 mega-amp of plasma current, its highest stored energy, and a fusion triple product up over 30% to about 8 x 10^18 m^-3 keV s - before entering a $52M upgrade co-funded with the U.S. Department of Energy and the UK's DESNZ that runs through most of 2026. On the magnet side, Demo4 became in November 2025 the first HTS magnet system to reproduce fusion-relevant fields at system level (11.8 tesla, 7 million ampere-turns), and in April 2026 Tokamak Energy was named Magnet Systems Partner for the UK government's STEP prototype power plant under a £70M contract running to March 2029. The company sells that magnet capability commercially through TE Magnetics, which acquired manufacturer Ridgway Machines in 2025 and has since diversified into non-fusion markets, including a 2025 contract with General Atomics to supply HTS magnets for a DARPA undersea-propulsion programme and an April 2026 study on using HTS to cut power-distribution losses in data centers. The company's roadmap runs ST40 to the ST80-HTS prototype at Culham and then to ST-E1, a pilot plant designed to put up to 200 MW of electricity on the grid in the early 2030s.

Founded 2009🇺🇰Milton Park, Oxfordshire, United Kingdom
Total Funding

$335M ($275M private + $60M UK/US government)

ST40 Plasma Current

1 MA (Dec 2025 record, up from 0.85 MA)

ST40 Triple Product

~8 (±2) x 10^18 m^-3 keV s (up 30%+ in the 2025 campaign)

Demo4 Magnetic Field

11.8 T with 7 million ampere turns (first HTS magnet system at fusion-relevant fields)

STEP Magnet Contract

£70M to March 2029 (Magnet Systems Partner, 8 work packages)

ST-E1 Pilot Plant Target

Up to 200 MW of net electricity, early 2030s

Granted Patents

300+ active patents

/ Upcoming Milestones

View all →

Complete SPARC assembly and commissioning

Close the external cryostat, integrate fuel and diagnostic lines, and complete final commissioning of the integrated tokamak, cryogenic, RF heating, and magnet systems at the Devens campus.

2026–2027

Move Fall Line Fusion Power Station through PJM interconnection study

Local land-use approval is already secured (Chesterfield County granted final zoning/conditional-use approval in September 2025). The remaining long-lead item is PJM Interconnection's multi-year (roughly 4-6 year) engineering study and approval process for the April 2026 grid-interconnection request, alongside locking down the final ARC plant design ahead of construction later this decade.

2026-2032

Scale the HTS magnet supply business

Execute the April 2026 Realta Fusion long-term HTS magnet supply agreement and turn the Type One Energy licensing deal, WHAM magnet supply, and Realta partnership into a recurring magnet business that funds the fusion roadmap before SPARC and ARC reach revenue.

2026+

Raise Polaris repetition rate toward 1 Hz

Push Polaris from one pulse every ~10 minutes toward sustained 1 Hz operation - the rate Helion needs to convert fusion energy into recapturable electricity in commercial operation.

2026–2027

Finalise the OpenAI gigawatt-scale supply deal

Move the OpenAI negotiations from term sheet to a binding agreement - reportedly 5 GW by 2030 scaling to 50 GW by 2035 - and identify the sites and Orion-class plants needed to deliver that capacity. Talks remained ongoing and unsigned as of August 2026, with site selection among the unresolved terms, and the arrangement has drawn Congressional and courtroom scrutiny over Sam Altman's personal stake in Helion and his recusal from the talks.

2026–2027

Pick the first plant site and start construction

Convert the April 7, 2026 completion of the Alabama/Ohio/Texas site evaluation tour into a final site choice and start construction of the initial ~50 MWe Da Vinci facility, contingent on the TMTG merger close (now targeted by end of 2026) and approvals. Re-verified as of late August 2026: no final site had been announced.

2026

/ Latest News

View all →