Aalo Atomics

Aalo-X

In Development

Aalo's experimental reactor campus at Idaho National Laboratory, built under the DOE Reactor Pilot Program. Its sodium-cooled Critical Test Reactor - a full-scale Aalo-1 core with 13 uranium-dioxide fuel assemblies - reached first criticality on July 4, 2026; the campus's follow-on Project Ascension reactor is intended to generate 10 MWe and power a co-located experimental data center.

Latest update Sep 8, 2026

Aalo-X

01

Current status

Critical Test Reactor achieved criticality July 4, 2026 - the fourth DOE-authorized advanced reactor to meet the Executive Order 14301 deadline - less than eight months after groundbreaking. Aalo's public technology roadmap now lists the first integrated 10 MWe Aalo-X power plant as a Q1 2027 milestone with groundwork complete, after the earlier end-of-2026 completion target slipped.

02

Specifications3

First criticality
July 4, 2026
Groundbreaking to criticality
Under 8 months
Planned output
10 MWe with co-located data center

first power targeted Q1 2027

03

Upcoming milestones2

Announced next steps from Aalo Atomics that mention Aalo-X.

  1. Q1 2027

    Complete the Project Ascension reactor at INL

    Finish the second, commercial-scale 10 MWe reactor on the Aalo-X campus and demonstrate full 10 MW output, ahead of integrating with the Crusoe-partnered Data Center Proving Ground later in 2027. Aalo's public technology roadmap now lists this first integrated power plant as a Q1 2027 milestone with groundwork complete, after the earlier end-of-2026 completion target slipped. The July 4 criticality post still frames 2027 as the year the new reactor produces electricity and powers an on-site data center.

  2. 2027

    Generate power for a co-located data center at INL with Crusoe

    Target2027 (POC); 2029 (commercial)

    Bring the Aalo-X campus to power operations so Project Ascension's 10 MWe reactor can feed an on-site experimental data center - the first nuclear plant purpose-paired with a data center. On July 30, 2026 Aalo named its first named data-center partner for this work, Crusoe: a 2027 proof-of-concept at INL will pair a 50 MWe Aalo Pod with a Crusoe Spark modular data center running Crusoe Cloud, with both companies targeting commercial nuclear-powered AI data center deployments by the end of 2029.

04

More from Aalo Atomics2

05

More in Nuclear Fission