Hermes

In Development
Kairos Power
Kairos Power
Hermes

Overview

35 MWth low-power demonstration reactor validating Kairos Power's KP-FHR design, construction methods, fuel program, and operating approach in Oak Ridge, Tennessee.

Construction permit granted in December 2023 and nuclear safety-related construction began in May 2025. In May 2026 the NRC extended the construction-completion deadline by 28 months to April 30, 2029 after first-of-a-kind site and design delays; Kairos now expects to finish building the reactor in 2028, pushing operation past the original 2027 target.

Key Specs

Thermal Output

35 MWth

Reactor Type

Fluoride salt-cooled high-temperature reactor (FHR)

Coolant

FLiBe (lithium fluoride-beryllium fluoride)

Fuel

HALEU TRISO pebble fuel

Location

Oak Ridge, Tennessee

Target Operation

~2028-2029 (construction now expected 2028)