
Proxima Fusion
Francesco Sciortino
Data verified as of Aug 1, 2026
Summary
Proxima Fusion is Europe's best-funded fusion company and the first research spin-off from the Max Planck Institute for Plasma Physics, founded in Munich in 2023 to commercialize the stellarator - a twisted magnetic bottle that is harder to build than a tokamak but runs continuously without needing to drive a current through the plasma. Its quasi-isodynamic design, Stellaris, was published in February 2025 as the first peer-reviewed, fully integrated stellarator power plant concept. In February 2026 Proxima signed a memorandum of understanding with RWE, the Free State of Bavaria and the Max Planck IPP to build Alpha, a roughly €2B net-energy demonstrator at Garching near Munich targeted to begin operating in 2031, followed by a commercial Stellaris plant at the decommissioned Gundremmingen nuclear site later in the 2030s; an Alpha Alliance of more than 30 European industrial companies including Siemens Energy, Framatome, Air Liquide and Thales was announced the day before. On July 7, 2026 the company raised €411M ($468M) at a €2.4B ($2.7B) valuation, led by XTX Ventures and East X Ventures with RWE and Google as strategic investors, taking total funding past €650M and funding completion of its Stellarator Model Coil in 2027.
Main Products

Proxima's quasi-isodynamic stellarator power plant concept, published in February 2025 as the first stellarator power plant design optimized simultaneously for plasma physics, engineering and maintenance and validated through peer review. Quasi-isodynamic optimization cancels the net toroidal current, which is what lets a stellarator run continuously and avoid the disruptions that plague tokamaks.
Design stage. The first commercial Stellaris plant is planned for the site of the decommissioned Gundremmingen nuclear fission station in Bavaria, with deployment targeted for the mid-to-late 2030s once Alpha has demonstrated net energy gain. Engineering design will be driven directly by data from Alpha.

Proxima's net-energy stellarator demonstrator, to be built at Garching near Munich next to the Max Planck Institute for Plasma Physics. Alpha is intended to be the first stellarator to achieve net energy gain (Q>1) and to prove out the manufacturing methods, materials and systems a commercial Stellaris plant would need.
Pre-construction. A February 2026 MoU with RWE, the Free State of Bavaria and Max Planck IPP set the financing and siting framework, and the Alpha Alliance of more than 30 European industrial companies was assembled to deliver the hardware. The July 2026 round funds the Stellarator Model Coil, the full-scale magnet demonstration due in 2027 that gates Alpha's construction.
What's Next
Complete the Stellarator Model Coil
Finish the Stellarator Model Coil, a full-scale high-temperature superconducting magnet demonstration that is the main hardware gate before Alpha construction. It is meant to de-risk HTS magnets for stellarator geometry, where coils are non-planar and far harder to manufacture than a tokamak's.
Scale HTS cable and magnet production
Use the July 2026 round to expand high-temperature superconducting cable and magnet manufacturing and the engineering systems behind stellarator production across the Munich, Paul Scherrer Institute and Culham sites, and hire across engineering, manufacturing and operations.
Convert the Alpha MoU into binding financing and permits
Turn the February 2026 memorandum of understanding with RWE, the Free State of Bavaria and Max Planck IPP into firm agreements: roughly 20% private financing, roughly 20% Bavarian co-financing against the up-to-€400M High-Tech Agenda, federal funding, and the permitting needed to build at Garching.
Bring Alpha online and demonstrate net energy gain
Build and commission the ~€2B Alpha demonstrator at Garching and operate it from 2031, aiming to make it the first stellarator ever to produce more fusion energy than it consumes and to generate the data that sets the Stellaris engineering design.
Operations & Revenue
No fusion device is operating yet. The company is building toward its Stellarator Model Coil, a full-scale HTS magnet demonstration targeted for completion in 2027 that is meant to de-risk stellarator magnets, while scaling HTS cable and magnet production across its Munich, Paul Scherrer Institute and Culham sites. Alpha, the ~€2B net-energy demonstrator at Garching, is in design with an MoU in place covering financing and siting and operations targeted for 2031; the commercial Stellaris plant at Gundremmingen follows later in the 2030s. Headcount is around 200 and growing across engineering, manufacturing and operations.
Pipeline & Contracts
More than €650M raised to date, including the July 2026 €411M round co-led by XTX Ventures and East X Ventures with utility RWE and Google investing strategically. RWE also brings power plant construction and operating expertise to the Alpha project.
Key Metrics
Timeline
On February 25, 2026 Proxima announces the Alpha Alliance, an industrial consortium of more than 30 European and international companies - including Siemens Energy, Framatome, Air Liquide, Thales, TRUMPF, Eni, Bilfinger, Pfeiffer Vacuum, Kyoto Fusioneering Europe and RWE Nuclear - assembled to manufacture, integrate and deliver the Alpha demonstrator's systems at scale.
On February 26, 2026 Proxima, utility RWE, the Free State of Bavaria and the Max Planck Institute for Plasma Physics sign a memorandum of understanding covering the roadmap to Europe's first commercial fusion power plant: Proxima leads engineering, procurement and construction and finances about 20% privately, Bavaria signals potential co-financing of about 20% (with up to €400M available through its High-Tech Agenda) plus permitting support, RWE contributes power plant construction and operating expertise, and IPP leads the plasma physics for Alpha.
On July 7, 2026 Proxima closes a €411M ($468M) financing round at a €2.4B ($2.7B) valuation, led by XTX Ventures and East X Ventures with RWE and Google joining as strategic investors alongside KfW Capital, SPRIND, Burda Principal Investments and returning backers including Plural, UVC Partners, Balderton, Cherry Ventures, Lightspeed and DST Global Partners. Total funding passes €650M including €95M of public grants, making Proxima Europe's best-funded fusion company.
Founded in April 2023 by Francesco Sciortino, Lucio Milanese, Jorrit Lion, Jonathan Schilling and Martin Kubie - scientists and engineers from the Max Planck Institute for Plasma Physics, MIT and X Development - as the institute's first research spin-off, with €7.5M in pre-seed funding from investors including Plural and UVC Partners.
Funding
Related Companies
All Nuclear Fusion
Commonwealth Fusion Systems
Nuclear Fusion
Commonwealth Fusion Systems is building commercial fusion systems around high-temperature superconducting magnet technology developed with MIT. SPARC, its fusion-energy demonstration tokamak under construction in Devens, Massachusetts, hit ~75% completion in 2026: the first of 18 toroidal-field magnets was installed in January and the second 48-ton vacuum-vessel half arrived in May, with all 18 magnets targeted by end of summer 2026 ahead of first plasma and a Q>1 net-energy attempt in 2027. ARC, CFS' first commercial plant - officially named the Fall Line Fusion Power Station and sited on 100 acres in Chesterfield County, Virginia - became in April 2026 the first fusion project to file for grid interconnection with PJM, and on June 4, 2026 CFS published a five-paper ARC Physics Basis in the Journal of Plasma Physics projecting ~1.1 GW of fusion power and ~400 MW of net electricity. CFS has also begun monetizing its HTS magnet platform, signing a potentially multi-billion-dollar long-term magnet supply deal with Realta Fusion and launching a SPARC digital twin program with Nvidia and Siemens, and in July 2026 became the first international partner in the UK Atomic Energy Authority's £220M LIBRTI tritium-breeding program to tackle fusion's fuel-supply challenge.

Helion Energy
Nuclear Fusion
Helion Energy is building fusion generators aimed at producing commercial electricity from fusion. Its Polaris prototype began operating in late 2024 and in February 2026 became the first privately developed fusion machine to demonstrate measurable deuterium-tritium fusion at 150 million degrees Celsius. Helion is now advancing Orion in Malaga, Washington, where site work began in 2025 for the company's first commercial machine intended to deliver electricity from fusion to Microsoft, while a smaller new 'Tiny Merge' testbed is being built to iterate on plasma formation faster. On June 4, 2026 Helion closed a $465M Series G led by Thrive Capital at a $15.5B post-money valuation, lifting total funding to roughly $1.5B; OpenAI is in advanced talks to buy fusion power from Helion at gigawatt scale, prompting Sam Altman to step down as board chair to recuse himself from those negotiations.

Pacific Fusion
Nuclear Fusion
Pacific Fusion is taking the inertial route to fusion rather than the magnetic one: instead of holding plasma in a magnetic bottle, it crushes a small capsule of deuterium-tritium fuel with an enormous, extremely fast electrical pulse. The company's distinguishing technology is the impedance-matched Marx generator, a pulser architecture that is simpler and cheaper than the systems used at national laboratories, and its plan is to gang 156 production-scale pulser modules into a Demonstration System designed to reach net facility gain - more fusion energy out than the total energy stored in the machine - by 2030. Founded in 2023 by Eric Lander, Keith LeChien, Will Regan, Carrie von Muench and Leland Ellison, it launched publicly in October 2024 with a roughly $900M Series A led by General Catalyst that is released in tranches against technical milestones; the round has since passed $1B as those milestones cleared. In June 2026 a scaled module prototype delivered more than 440 gigawatts at about 1.1 megavolts in an 80-nanosecond pulse, and in July 2026 the Sirius prototype at Lawrence Livermore National Laboratory passed 3,000 full-power shots at 95% energy efficiency. Its $1B research and manufacturing campus at Mesa del Sol in Albuquerque, New Mexico, backed by a build center in Los Lunas, is where the Demonstration System will be assembled.

TAE Technologies
Nuclear Fusion
TAE Technologies is a private fusion company developing hydrogen-boron fusion with a beam-driven field-reversed-configuration architecture. Its 2025 'Norm' breakthrough reduced reactor complexity enough to skip the planned Copernicus step and move directly toward Da Vinci, its first prototype power plant. In 2026 TAE completed its multi-state site evaluation tour for the first 50 MWe plant (Alabama, Ohio, Texas), formally established the TAE Beam UK joint venture with UKAEA at Culham to commercialize neutral-beam accelerator technology, and is now targeting a Q4 2026 close of its $6B all-stock merger with Trump Media & Technology Group, which in June 2026 confirmed it will no longer spin off Truth Social and other media assets ahead of the deal. TAE Power Solutions and TAE Life Sciences commercialize adjacent power-delivery and oncology technologies derived from its fusion R&D.

Tokamak Energy
Nuclear Fusion
Tokamak Energy is a UK fusion company spun out of the UK Atomic Energy Authority in 2009 that pairs two bets: the spherical tokamak, a squashed-sphere reactor shape that holds plasma more efficiently than a conventional doughnut, and high-temperature superconducting (HTS) magnets built in-house. Its ST40 machine reached 100 million degrees Celsius in 2022 and closed out its 2025 campaign with three records - 1 mega-amp of plasma current, its highest stored energy, and a fusion triple product up over 30% to about 8 x 10^18 m^-3 keV s - before entering a $52M upgrade co-funded with the U.S. Department of Energy and the UK's DESNZ that runs through most of 2026. On the magnet side, Demo4 became in November 2025 the first HTS magnet system to reproduce fusion-relevant fields at system level (11.8 tesla, 7 million ampere-turns), and in April 2026 Tokamak Energy was named Magnet Systems Partner for the UK government's STEP prototype power plant under a £70M contract running to March 2029. The company sells that magnet capability commercially through TE Magnetics, which acquired manufacturer Ridgway Machines in 2025, and its roadmap runs ST40 to the ST80-HTS prototype at Culham and then to ST-E1, a pilot plant designed to put up to 200 MW of electricity on the grid in the early 2030s.