Radiant Nuclear logo

Radiant Nuclear

PrivateFounded 2020🇺🇸1921 E. Maple Ave, El Segundo, CaliforniaCEO Doug Bernauer

Radiant is still pre-revenue on Kaleidos sales. A 9 October 2026 deep audit found no public announcement that the Kaleidos Development Unit was installed, fueled, or taken to zero-power criticality at INL DOME after Q3 closed on 30 September.

Latest update Oct 9, 2026

01

Overview

The news index still tops out at the 9 September Centrus HALEU contract and the 12 August El Segundo departure. Wikipedia still records the August shipment, not criticality. The NRC Kaleidos page, last reviewed 15 September, remains pre-application; the KDU commissioning plan is under review and the R-50 Part 70 application is in RAI. NRIC says DOME is currently hosting Kaleidos and next availability begins July 2027, while another FAQ line still says testing likely in 2027; neither is a criticality result. No sourced revised campaign date. Janus is up to $750 million for 15 units; Fort Benning remains three 1 MW units with the pad still under evaluation; Buckley remains the 2028 ANPI site.

radiantnuclear.comUpdated Oct 9, 2026

Analysis · 4 min read · Oct 7, 2026The long view on Radiant Nuclear: strategy, technology and what to watch

02

What's next6

  1. Q3 2026

    Complete the DOME five-phase test campaign

    After installation and fueling at INL's DOME, progress through zero-power criticality, 1 MW thermal, full-power/full-temperature operation, and a minimum 150-hour unattended run. Radiant targeted completing that campaign in Q3 2026. As of September 18, 2026 no criticality announcement had been published, so the Q3 window is tight and may slip into Q4.

  2. Q3 2026

    Announce Kaleidos zero-power criticality at INL DOME

  3. Q4 2026

    File a Kaleidos operating-license application

    Radiant's regulatory engagement plan says it will submit an operating-license application for Kaleidos at R-50 in Q4 2026, separate from the Part 70 materials license now under review. NRC pre-application (docket 99902106) has been open since October 2022. As of September 18, 2026 no operating-license application was on file.

  4. Dec 18, 2026

    Win the R-50 Part 70 special-nuclear-material license

    The NRC accepted Radiant's 10 CFR Part 70 application for the Oak Ridge fueling building on May 1, 2026 and, in a July 27 Federal Register notice, dated its license determination to December 18, 2026. Radiant has said it is targeting commissioning of R-50 in January 2027. A Part 70 license is for possessing and loading fuel, not a commercial reactor operating license.

  5. 2028

    Deliver the first Kaleidos to Buckley Space Force Base

    ANPI selection on April 22, 2026 names Buckley SFB in Aurora, Colorado as the proposed site, with first Kaleidos reactors targeted for 2028. Siting and NEPA analysis have not finished. Radiant frames this as America's first commercially developed microreactor at a military installation.

03

Products2

04

Key metrics

Employees
~200

(TrueUp estimate, 2026); Wikipedia listed 100 as of 2025; LinkedIn company size 51-200

Est. annual revenue
Pre-revenue from reactor sales

Janus is a milestone-based development-and-deployment contract up to $750M, not current product revenue

Total Raised

~$516M+ disclosed equity through the December 2025 Series D, plus an undisclosed Lockheed Martin Ventures add-on in February 2026; Wikipedia and the Los Angeles Business Journal put the 2026 total over $575M

Valuation
$1.8B+ post-money

Series D, December 2025

Kaleidos Output
1 MWe / ~3 MWth

(NRC); 1.9 MW usable thermal for heat or desalination (company)

Janus Award
Up to $750M for 15 Kaleidos units

largest Janus award; Fort Benning named

R-50 Factory

300,000 sq ft / ~80-acre Oak Ridge campus, targeting 50 reactors per year; Part 70 review due December 18, 2026

DOME campaign status
No public criticality as of 27 Sept 2026
DOME campaign status after Q3

No public install, fueling, or zero-power criticality as of 2 Oct 2026; Q3 target closed without a sourced revised date

DOME campaign status after 9 Oct deep audit

No public install, fueling, or zero-power criticality as of 9 Oct 2026; news still 9 Sept Centrus; NRC last reviewed 15 Sept still pre-application

05

Operations & revenue

Operating status

Pre-revenue

As of 9 October 2026 Radiant has not announced that the Kaleidos Development Unit was installed, fueled, or taken to zero-power criticality at INL DOME. Q3 2026 ended 30 September. The news index still tops out at the 9 September Centrus HALEU contract. The NRC Kaleidos page, last reviewed 15 September, remains pre-application; the KDU commissioning plan is under review; the R-50 Part 70 application is in RAI (Set 2 ML26216A291 issued). NRIC currently-hosting is internally contradicted by a testing-likely-2027 line and is not a criticality announcement. ANS 2 October named Deployable Energy next in DOME after Radiant's first 2026 slot and did not report a Radiant criticality. Wikipedia records the August shipment. No commercial Kaleidos is operating.

Pipeline & contracts

  • Military microreactor deployments (contracted / planned)

    Up to $750M Janus agreement with the Army and DIU for 15 Kaleidos units, with Fort Benning as the named site and deployments framed through 2030. Separate ANPI selection to develop and operate reactors at Buckley Space Force Base, with first deliveries targeted for 2028. Both are development-and-deployment programs, not yet operating plants.

  • Commercial Kaleidos sales (planned)

    Factory-built 1 MWe portable reactors sold or contracted to data centers, remote industry, hospitals, and off-grid sites. Equinix has a deposit-backed agreement for 20 units. Radiant says it will fuel, refuel, and store spent fuel at its own facilities so customer sites never hold spent fuel.

  • DOE demonstration work

    Exclusive year-long access to INL's DOME test bed for a full-scale, full-power Kaleidos campaign, plus a second DOE HALEU allocation announced July 23, 2026 and selection for the Nuclear Energy Launch Pad.

06

Timeline13

  1. 2026

    1. RAFT ATR fuel test prepared in parallel with DOME

      Idaho National Laboratory, writing in ANS Nuclear Newswire on September 18, 2026, said Radiant is preparing the Radiant ATR Fuel Test (RAFT) in the Advanced Test Reactor using HALEU TRISO fabricated by Standard Nuclear. RAFT is meant to qualify Kaleidos fuel to higher burnup than the DOME campaign can provide, because that demonstration is scheduled to last months rather than years. The same article still described DOME reactor tests as upcoming and captioned TRISO fuel as delivered for those upcoming tests, which is not a criticality or later-phase result.

    2. Locks TRISO through the early 2030s; Centrus HALEU contract

      On August 20, 2026 Radiant signs a long-term TRISO fabrication agreement with Standard Nuclear through the early 2030s. On September 9 it signs a definitive multi-year HALEU supply contract with Centrus, with deliveries before the end of the decade and prepayments to support Piketon expansion, adding a U.S.-origin unobligated enrichment path for national-security deployments.

    3. $750M Army Janus award for 15 Kaleidos units

      On August 26, 2026 the Army and DIU execute a binding agreement totaling up to $750M for Radiant to develop and deploy 15 Kaleidos reactors under Janus - Radiant says it is the largest award in the program and one of DIU's largest contracts. The named site is Fort Benning, Georgia; deployments are framed through 2030. The Army's broader Janus awards total up to $2.2B across five vendors.

    4. TRISO fuel arrives at DOME; Kaleidos shipped to Idaho

      On July 1, 2026 Standard Nuclear-fabricated TRISO fuel arrives at INL's DOME facility. On August 12 the Kaleidos Development Unit leaves El Segundo on a trailer for the more than 1,000-mile road trip to DOME, where Radiant plans a five-phase campaign through zero-power criticality, 1 MW thermal, full power, and a 150-hour unattended run.

    5. NRC accepts R-50 Part 70 application

      On May 1, 2026 the NRC accepts Radiant's 10 CFR Part 70 special-nuclear-material license application for the Oak Ridge R-50 fueling building for detailed review, aiming to finish about 55% faster than the standard schedule. A Federal Register notice later dates the staff's license determination to December 18, 2026.

    6. Buckley Space Force Base selected under ANPI

      On April 22, 2026 the Department of the Air Force and DIU select Radiant to develop and operate Kaleidos reactors proposed for Buckley Space Force Base in Aurora, Colorado, with first deliveries targeted for 2028. Next steps include NEPA siting and environmental analysis.

    7. DOE PDSA-equivalent approval; Lockheed Martin Ventures invests

      On February 9, 2026 DOE approves Radiant's DOE Authorization Request for Kaleidos, meeting the intent of a Preliminary Documented Safety Analysis for a full-power DOME test. On February 17 Lockheed Martin Ventures joins the oversubscribed round as a strategic investor (amount undisclosed).

  2. 2025

    1. $300M+ Series D at $1.8B valuation; Equinix orders 20 units

      On December 17, 2025 Radiant raises more than $300M led by Draper Associates and Boost VC, with Founders Fund, ARK Venture Fund, Chevron Technology Ventures, and others, at a valuation of more than $1.8B. The company says Equinix has signed a deposit-backed deal for 20 Kaleidos reactors.

07

Funding

$516Mdisclosed across 6 rounds with a stated amount

Cumulative disclosed raise · dated rounds

$200M$400M$600M202120222023202420252026$516M raised
  1. Angel

    September 2020

    $1.2M

    Hank Vigil, Josh Manchester, Thomas McInerney, Charlie Songhurst, other angels

  2. Series A

    March 2022

    $10M (company figure; Not Boring later described the round as $11M)

    Union Square Ventures (lead), Boost VC, Cantos Ventures, Tribe Capital, Decisive Point, McKinley Capital, JAM Fund, Nucleation Capital, Also Capital, DCVC

  3. Series B

    April 2023

    $40M

    Andreessen Horowitz (lead), Founders Fund, Decisive Point, McKinley Capital, Draper, Cantos Ventures, Boost VC

  4. Series C

    November 2024

    $100M

    DCVC (lead, Rachel Slaybaugh), Andreessen Horowitz, Union Square Ventures, Felicis, Washington Harbour Partners, Chevron Technology Ventures, Founders Fund, Decisive Point, McKinley Alaska, Boost VC, Also Capital

  5. Series C extension

    May 2025

    $65M, taking Series C to $165M and total venture funding to $225M

    DCVC, Giant Ventures, StepStone, ARK Venture Fund, Align Ventures, Crossbeam Venture Partners, Gigascale Capital, HartBeat Ventures, Pax Ventures, SGA Capital, others

  6. Series D

    December 2025

    $300M+ at $1.8B valuation

    Draper Associates (co-lead), Boost VC (co-lead), Founders Fund, ARK Venture Fund, Chevron Technology Ventures, Friends & Family Capital, others

  7. Series D add-on

    February 2026

    Undisclosed

    Lockheed Martin Ventures (strategic)

All Nuclear Fission