Antares Nuclear

Mark-0

In Development

A full-scale, zero-power demonstration of the R1 core at Idaho National Laboratory's RACE facility, built under DOE's Reactor Pilot Program. It has no power conversion or heat-removal loop; the test validated reactor physics, control-drum behavior, and the DOE authorization pathway using BWXT-fabricated HALEU TRISO.

Latest update Sep 18, 2026

Mark-0

01

Current status

Achieved initial (zero-power) criticality on June 4, 2026. Not an electricity-producing plant. Antares plans to reuse the same INL facility and fuel batch for the Mark-1 electricity-producing reactor in 2027.

02

Specifications3

First criticality
June 4, 2026
Power level
Zero-power physics test

no electricity, no active heat removal

Location
INL Reactor and Critical Experiment

(RACE) facility, Idaho

03

Upcoming milestones1

Announced next steps from Antares Nuclear that mention Mark-0.

  1. 2027

    Produce electricity with Mark-1 at INL

    Operate a full-power, electricity-producing advanced reactor at the same INL test facility used for Mark-0, using the same HALEU TRISO batch and a nitrogen closed Brayton cycle. Antares has said Mark-1 is scheduled to operate for more than six months in 2027. As of September 18, 2026 this remained a company target, not a started campaign.

  1. US private microreactor hits criticality first under Trump DOE pilot

    Antares Nuclear's Mark-0 sodium heat-pipe microreactor achieved zero-power criticality at Idaho National Laboratory on June 4, 2026, becoming the first privately developed advanced reactor to reach that milestone under the Department of Energy's Reactor Pilot Program - a Trump executive-order initiative targeting at least three advanced reactor criticalities by July 4. The Mark-0 is fueled by HALEU TRISO compacts and uses a heat-pipe-cooled, fast-spectrum design initially targeting U.S. military bases, with commercial electricity sales targeted for late 2027 and full deployment by end of 2028 - at the same Idaho National Laboratory campus where Oklo is constructing its Aurora powerhouse under an NRC-issued combined construction and operating license. The DOE has selected eleven advanced reactor projects under the RPP, and the Antares milestone validates the regulatory testing infrastructure and fast-fission design path that underpins the broader U.S. advanced nuclear build-out.

    BusinessWire PBS NewsHour Power Magazine + Oklo