Boom Supersonic

Superpower

Pre-production

42 MW natural-gas turbine derived from the same core engine technology as Symphony, with about 80% hardware commonality. Superpower is designed for AI data centers and other onsite power applications, emphasizing waterless operation and strong output in hot, dry environments.

Latest update Sep 20, 2026

Superpower

01

Current status

Boom revealed Superpower in December 2025 with Crusoe as launch customer for 29 turbines worth $1.25B+. Aviation Week reported on September 8, 2026 that the shared Symphony sprint core is nearing completion and expected to begin ground tests at Watkins, Colorado, within two months, a slip out of the original Q3 2026 window into roughly November, ahead of end-2026 assembly of a fully integrated 42 MW pre-production turbine and operational readiness in H1 2027. First customer deliveries to Crusoe are targeted for late 2027. Baker Hughes is supplying 31 generators totaling 1.3 GW to pair with the turbines.

02

Specifications7

Power Output
42 MW
Launch Order
29 turbines / 1.21 GW (Crusoe)
Operating Profile
Waterless; full output above 110°F
Fuel
Natural gas with backup diesel
Symphony Hardware Commonality
~80%
First Deliveries
Late 2027 (Crusoe)
Production Ramp Plan
1 GW (2028) → 2 GW (2029) → 4 GW (2030)

03

Upcoming milestones4

Announced next steps from Boom Supersonic that mention Superpower.

  1. Nov 2026

    Finish Symphony sprint core and run the first ground-test cycle

    CEO Blake Scholl said in late August 2026 that Boom was a few weeks from running the Symphony sprint core for the first time at the Colorado Air and Space Port. Aviation Week reported on September 8 that the prototype high-pressure core is nearing completion and is expected to begin ground tests at Watkins, Colorado, within two months, a slip out of the original Q3 2026 window into roughly November. The 14,000-pound stand-alone test article covers the high compressor, combustor, and high turbine, the key technical gate for de-risking both Symphony and the Superpower turbine.

  2. End of 2026

    Assemble first integrated 42 MW Superpower pre-production turbine

    TargetEnd of 2026 (assembly); H1 2027 (operational)

    Use the sprint core results to assemble a fully integrated 42 MW pre-production Superpower turbine by the end of 2026 and reach operational readiness in the first half of 2027 ahead of the first Crusoe deliveries.

  3. 2027

    Deliver first Superpower turbines after Crusoe exit

    TargetAbout 250 MW in 2027 to unnamed sites; 1 GW company target in 2028

  4. Late 2027

    Deliver first Superpower units to Crusoe

    TargetLate 2027 (first deliveries); 2030 (4 GW/yr)

    Begin handing over the first units from the 29-turbine, $1.25B+ Crusoe order in late 2027 (per CEO Blake Scholl in June 2026), then ramp Superpower production toward 1 GW in 2028, 2 GW in 2029, and 4 GW in 2030 to fund Overture development.

  1. Crusoe drops $1.25B Boom Superpower turbine launch order

    Boom CEO Blake Scholl said on Sept. 25 that Crusoe is no longer the launch partner for Superpower, Boom's 42 MW data-center turbine, because turbines are no longer part of Crusoe's near-term power mix at Abilene and other sites. Crusoe had been described as ordering 29 turbines worth $1.25 billion with first deliveries in 2027; Crusoe confirmed to TechCrunch it is no longer doing business with Boom. Scholl said Boom still expects to deliver about 250 MW of Superpowers next year to other unnamed sites and is targeting 1 GW in 2028.

    techcrunch.com

  2. Boom targets late 2027 for first AI-data-center power turbines

    Boom Supersonic is targeting the end of 2027 to ship the first five units of its Superpower ground turbines, founder and CEO Blake Scholl said at the AIAA AVIATION Forum on June 11. Each Superpower generates 42 megawatts - which Boom argues is enough to power the AI data centers being built across the U.S. - and the units are derived from the same core the company developed for the Symphony engines that will power its Overture supersonic airliner. Boom says it already holds about $1.2 billion in orders for the natural-gas turbines, an adjacent business line that monetizes its propulsion R&D ahead of Overture's entry into service.

    Aerospace America (AIAA)

05

More from Boom Supersonic2

06

More in Civilian Aircrafts